Manufacturing Company
This project primarily comprises a 15.7 MW Gas Turbine Generator (Solar Titan 130), a Heat Recovery Steam Generator with a capacity of 120,000 lb/hr, featuring duct burners and fresh air firing, as well as exhaust heat recovery for the tissue drying process.
The supporting equipment encompasses a Fuel Gas Booster Compressor (FGBC), an emergency diesel genset, a 15 MVA transformer, and 27.6 kv switchgear.
CEM played a pivotal role in all stages of this project’s development, from its inception to providing post-completion support. Our support services encompassed feasibility studies, including capital expenditure budgets and business case performance, assistance with financial incentive applications, permitting, technical coordination with local utilities, detailed engineering, commissioning, and construction support.
Noteworthy aspects of this project include electrical islanding, facility and equipment design that meets rigorous local noise requirements in a densely populated urban area, and a seamless transition from turbine exhaust gas (TEG) mode to fresh air fire mode (FAF) for the HRSG’s online operation.