CEM Responsibilities
- Early Technical and Economic Feasibility Studies; subsequent detailed engineering and construction management services
- Managed all Permits and Approvals, Building Permits, and liaison with Ministry of Environment
- Managed Certificate of Approval, accounting for air and noise emissions
- Provided engineering support and project management services for major equipment selection and procurement.
- CEM was responsible for hot water tie-in to existing greenhouse loads and hot water loop for digester heating; biogas piping, biogas boiler fuel train, and biogas blower to engine genset and greenhouse boiler system.
- Obtaining approval from TSSA for biogas fuel system and piping
- Design of biogas clean up system, to ensure biogas meets quality requirements of engine.
- Facilitated Net-Metering arrangement with Peninsula West Utilities; arranged installation of second revenue grade meter for RESOP Contract
- Prepared RESOP application to the OPA.