GLOBAL ADJUSTMENT PROJECT: This project was specifically implemented to reduce Global Adjustment costs. With its implementation, Client should save approximately $4.2 million/year.

NATURAL GAS GENERATOR INSTALLATION: This project features ten (10) natural gas generators. CEM procured, implemented/installed and commissioned the natural gas generators.

CONTAINER: This CHP system is containerized.

PARTNERS: This project was completed in partnership with Stolk Construction.

Project Details

SIZE

830 KWE EACH

CLIENT

Automotive

NUMBER OF UNITS

10

MAKE/ MODEL

GUASCOR SFGRD 560