ADM

The project consists of two cogeneration systems each equipped with one combustion turbine generator (GTG) and one heat recovery steam generator (HRSG). Each GTG is derated to 4.6 MW, to produce electricity (total of 9.2 MWe) and steam for use on site. The 4.6 MWe rated GTGs are based on units capable of delivering 5.4 MWe (nominal) of electricity for continuous duty.

CEM Engineering was involved from the feasibility study stage of the project and engaged as Engineering and Construction Management to deliver the project.