Basaltic – Energy Storage Project
CEM Engineering is developing a 5 MW/20 MWh battery energy storage project in response to the IESO’s LT1 Request for Proposal (RFP). This project will be co-located with an existing solar PV facility and will provide up to four (4) hours of energy resiliency to the local electrical distribution system.
Project Details
NAMEPLATE CAPACITY
5 MW
TECHNOLOGY
Battery Energy Storage System
LEGAL NAME OF PROPONENT
Cogeneration and Energy Management Engineering Inc. (d/b as CEM Engineering)
CONTACT INFO OF PROPONENT
Matt Lensink, matt@cemeng.ca, 289-668-4364